Above Ground Storage Tank & Terminal Cleaning

Your tank cleaned, inspection-ready, with nobody inside it.

PMI cleans above-ground storage tanks for terminals, chemical plants and refineries across the Gulf Coast and beyond: crude, refined products, chemicals and bulk food liquids.

Above ground storage terminal at sunrise with large external floating-roof tanks and rows of white storage tanks

The record

  • 24 hrtypical mobilization
  • 8.5M galper tank cleaned at a Texas terminal
  • $1,000/daysaved on rescue coverage
  • 50+years in operation
  • 2-yearterminal contract awarded by corporate procurement
Tank cleaning equipment layout at an AST terminal

The problems this ends

  • Every day a tank sits dirty is storage revenue lost and an inspection deadline closer.

  • Confined-space entry is your highest-risk permit. The safest entry is one nobody makes.

  • Trucking wash water off site multiplies cost, liability and your environmental footprint.

  • Contractors who are not in your vendor system can stall a project for weeks.

Scope of work

What you get

Automated, non-entrant cleaning where the tank allows it, disciplined conventional crews where it does not, and wash water treated and reused on site with our EC-AOP system.

Watch it run

In-tank camera: RoosterEX heads washing out tank-bottom solids while the crew stays outside the tank.
  1. Automated (non-entrant) tank cleaning

    RoosterEX automation removes entry time where tank geometry allows. The philosophies are the same: remove entry time, no people in tank.

  2. Conventional cleaning crews

    Multiple cross-trained crews of 2 to 12+, and scalable from our Port Fourchon operations housing 60 to 80 persons if additional personnel are ever needed.

  3. Confined space rescue attendants

    In-house rescue coverage through cleaning, inspection and repair. Saved one terminal client $1,000 per day versus a third party.

  4. EC-AOP wash-water treatment on site

    Hydrocarbons and suspended solids removed at the tank; water reused, not trucked off.

  5. Ventilation and isolation

    Included scope, not a change order.

  6. Turnkey coordination

    All-in pricing available. Scaffolding and waste hauling are third-party coordinated and billed direct to you.

The procedure

How the job runs

The sequence below is the one our supervisors and crews work to on this scope. Readings, permits and sign-offs are documented as the job moves through it.

  1. Before we arrive

    We send the facility a current training matrix and personnel mobilization forms. Once your side approves the people, every work group and vendor attends your facility orientation, and we hold a pre-job meeting at the tank with everyone who will be involved. JSAs are written and reviewed for equipment inspection, equipment setup, de-inventory of remaining waste and the isolation work. All equipment is grounded and function tested before first use.

  2. Isolation

    Double block and bleed per the isolation plan, blinds and skillets installed under lockout and tagout. Isolation is verified by every work group involved and re-verified with your assigned personnel, then personnel locks go on.

  3. Positive isolation

    Spill containment goes in before any flange is broken: containment pans under every break point, berms and absorbent staged. Tags are ready before the blinds and skillets go in. Rigging, mechanical devices and straps are inspected and the load weight verified before anything is moved.

  4. Flood to water-draw height

    Water goes in through the tank's 2-inch water-draw connection, or through a top connection installed under supplied air, using a 2-inch diaphragm pump. At height we stop and pump down to the oil water separator, which holds 1,000 gallons and handles a minimum of 50 GPM.

  5. Top manway wash

    Nozzles go into the tank through the 20-inch top manway with the manway sealed off, crews on supplied breathing air. Material is pumped down from the water draw to the waste frac tank.

  6. Degassing

    A third party mobilizes a direct-fire thermal oxidizer for vapor control, connected to a top flange with a knock-out pot in line so no liquid can reach it, on its own generator. Inlet and outlet VOC and LEL readings are taken every 30 minutes and logged, and the tank LEL is checked throughout. Degassing is complete when the reading is confirmed under 5 percent LEL.

  7. Non-entry purging

    Once LEL is under 50 percent, nozzles go in at the bottom manway under supplied air to help the degassing along and move sediment. The waste is liquefied so it can be pulled out and discharged to the waste frac tank. Crews remove what they can reach without breaking the plane of entry.

  8. Ventilation

    A 20-inch blower goes on the top manway opening and pulls outside air in through the bottom opening, flushing the remaining vapor out the top.

  9. Bottom manway cleaning, from outside the tank

    The confined space entry permit is completed, the blower is shut down, and the supervisor tests the atmosphere through the bottom manway with a gas monitor. Results are documented and the blower restarts. Personnel working the opening are on supplied air with full body harness and protective clothing, and monitoring is continuous. Waste near the manway comes out with water pressure, vacuum, 6-foot aluminum squeegees and brass shovels.

  10. Confined space entry

    The supervisor walks the crew through the JSA and a detailed rescue plan, ventilation is shut down for an accurate atmospheric test, and the entry permit is completed. Entrants go in through the bottom manway on supplied air in full harness and protective clothing. A hole watch and rescue personnel stay stationed at the manway for the entire entry, the hole watch never leaves the post, and every entry and exit is logged. Sludge and solids come out with vacuum and washdown, walls and floor are cleaned with a hot or cold water blast unit, and cleaning height is no less than 3 feet and higher where what we see calls for it. The tank is washed with detergent, then you and PMI walk it together before anything is rigged down.

  11. Disposal

    All waste from the tank and from the cleaning goes into the frac tank. When it is ready to move, a vacuum truck is dispatched to your approved disposal site. Used PPE is drummed and goes the same way.

  12. Demobilization

    Both manways reinstalled, skillets removed and piping restored, personnel locks off, equipment rigged down, work area cleaned, trash and oily rags and absorbent pads in proper waste containers, and the area swept for debris.

PMI crew in a job safety briefing beside a MudHog unit
StepEvery work group in the pre-job meeting before anything is rigged up.
PMI operator holding RoosterEX cleaning heads at the open RoosterEX trailer, with more heads racked inside
StepRoosterEX heads ready to go in at the top manway. The crew runs them from outside the tank.
PMI rescue team rigging a tripod and retrieval winch over a confined space entry
StepRescue team rigs the tripod and retrieval winch before anyone enters.
PMI vacuum tank truck staged in the yard beside frac boxes
StepVacuum truck staged to haul waste to your approved disposal site.

Questions we get

Above Ground Storage Tank & Terminal Cleaning FAQs

How fast can you mobilize?

Usually within 24 hours.

What size crews do you run?

2 to 12+ per job, cross-trained. For larger scopes we pull from our Port Fourchon operations, which house 60 to 80 people.

Can you give a turnkey, all-in price?

Yes. Scaffolding and waste hauling are third-party services we coordinate; we prefer those billed directly to you.

What drives cost?

Tank size, the product it held, and how much product remains after pump-off.

Do your people have to enter the tank?

Where tank geometry allows automated cleaning, no. Where entry is required, entries are minimized and covered by our own confined-space rescue attendants.

What happens to the wash water?

Our EC-AOP unit treats it at the tank: hydrocarbons and suspended solids out, water reused on site instead of trucked away.

We do not have an MSA with PMI. How long does onboarding take?

We return the documentation your procurement team needs within 24 hours, and we can often begin sooner through an approved affiliate already in your system.

Do you provide ventilation?

Yes, as part of the cleaning scope.

Do you do coatings or inspections?

No. We hand the tank over clean and ready so your inspection and coating contractors start on schedule.

Tell us about the tank. We will have numbers back to you fast.

Send the tank size, last product, and your window. Quotes routed same day to our estimating team; 24/7 dispatch for urgent work.